Year-by-year milestones, September 2026 through August 2031

The project runs two full breeding-to-field cycles over five years. Milestones below are as committed in the approved project plan. This page is updated as milestones are met.

Year 1 · 2026–2027

  • Governance established; trainees recruited
  • Stakeholder Advisory Board formalized; commercial MOUs signed
  • Broodstock conditioning and priming begin at all three coastal sites
  • Baseline metabolic phenotyping complete
  • Shared data schemas and GitHub organization established; PRISM Portal wireframes

Year 2 · 2027–2028

  • Cycle 1 spawning: pedigreed families from primed and control parents
  • Field deployments begin at contrasting sites on all three coasts
  • First regional workshops
  • Prototype dashboard delivered; Stakeholder Advisory Board review
  • Trainee rotations start; formative evaluation

Year 3 · 2028–2029

  • 12-month Cycle 1 field performance data complete
  • Cycle 2 launched with refined protocols
  • Machine-learning predictive models trained
  • Beta dashboard and PRISM Portal released
  • Sustainability planning begins

Year 4 · 2029–2030

  • Models and priming protocols validated on independent Cycle 2 data
  • Dashboard and PRISM Portal publicly released
  • ADAPT micro-credential piloted
  • At least 3 hatcheries priming commercially
  • Second formative evaluation

Year 5 · 2030–2031

  • National capstone workshop
  • Final publications, target of at least 8
  • Implementation manuals and cost–benefit analyses delivered
  • Open data and code repositories released
  • Summative external evaluation and final report

Standing commitments

Quarterly all-investigator teleconferences, semi-annual Stakeholder Advisory Board meetings, an annual in-person meeting at a rotating partner site, and annual NIFA progress reports.