Timeline
Year-by-year milestones, September 2026 through August 2031
The project runs two full breeding-to-field cycles over five years. Milestones below are as committed in the approved project plan. This page is updated as milestones are met.
Year 1 · 2026–2027
- Governance established; trainees recruited
- Stakeholder Advisory Board formalized; commercial MOUs signed
- Broodstock conditioning and priming begin at all three coastal sites
- Baseline metabolic phenotyping complete
- Shared data schemas and GitHub organization established; PRISM Portal wireframes
Year 2 · 2027–2028
- Cycle 1 spawning: pedigreed families from primed and control parents
- Field deployments begin at contrasting sites on all three coasts
- First regional workshops
- Prototype dashboard delivered; Stakeholder Advisory Board review
- Trainee rotations start; formative evaluation
Year 3 · 2028–2029
- 12-month Cycle 1 field performance data complete
- Cycle 2 launched with refined protocols
- Machine-learning predictive models trained
- Beta dashboard and PRISM Portal released
- Sustainability planning begins
Year 4 · 2029–2030
- Models and priming protocols validated on independent Cycle 2 data
- Dashboard and PRISM Portal publicly released
- ADAPT micro-credential piloted
- At least 3 hatcheries priming commercially
- Second formative evaluation
Year 5 · 2030–2031
- National capstone workshop
- Final publications, target of at least 8
- Implementation manuals and cost–benefit analyses delivered
- Open data and code repositories released
- Summative external evaluation and final report
Standing commitments